4 men and 5 women can complete a work in 15 days, whereas 9 men and 6 women can do it in 10 days. To complete the same work in 7 days, how many women should assist 4 men?
The height of a house subtends a right angle at an opposite window & the line through the window to the top of the house makes an angle θ with the vertical. If the breath of the street be ‘d’ meters. Find the height of the house
A can do a piece of work in 6 days. B can do it in 9 days. With the assistance of C they completed the work in 3 days. In how many days can C alone do the work ?
Five men and 2 boys can do as much work in 30 days as 7 men and 10 boys can do in 15 days. How many boys should join 40 men to do the same work in 4 days?